Job Description:
Electrical & Instrumentation Works
Project Duration:
July 2018 – January 2021
Project Highlights:
- Manhours: 330.000
- Manpower Peak: 250
- Key Quantities Installed
- Electrical Works
Cable Trays: 14.500 lm
MV/LV Cables Laying: 172.000 lm
MV/LV Cables Connection: 3.200 no.
Lighting Fixtures: 1.300 no.
MV/LV Panels: 110 no. - Instrumentation Works
Cable Trays: 21.000 lm
Ins Cables Laying: 326.000 m
Multicables Connection: 2.820 no.
Junction Boxes: 350 no.
Field Instruments: 2.200 no.
Loop Checks: 3.325 I/O
- Electrical Works