Job Description:
Electrical & Instrumentation Works
Project Duration:
December 2010 – June 2012
Project Highlights:
- Manhours: 525.000
- Manpower Peak: 260
- Key Quantities Installed:
- Electrical Works
Cable Trays: 20.000 lm
Cable Conduits: 13.500 lm
Grounding System: 60.000 lm
MV/LV Cables Laying: 425.000 lm
Lighting Fixtures: 2.800 no.
Equipment: 367 no. - Instrumentation Works
Ins Cables Laying: 640.000 lm
Cable Conduits & Trays: 42.000 lm
Junction Boxes: 372 no.
Field Instruments: 6.500 no.
Control Valves: 800 no.
Equipment: 327 no.
Loop Checks: 9.730 I/O
- Electrical Works