Job Description:
Electrical & Instrumentation Works
Project Duration:
November 2017 – March 2019
Project Highlights:
- Manhours: 140.350
- Manpower Peak: 110
- Key Quantities Installed:
- E&I Works
Cable Trays: 19.000 lm
MV/LV Cables Laying: 91.000 no.
Lighting Fixtures: 396 no.
MV/LV Panels & Equipment: 196 no.
Ins Cables Laying: 67.000 m
Field Instruments: 1.300 no.
- E&I Works