Job Description:
Electrical & Instrumentation Works
Project Duration:
November 2012 – December 2015
Project Highlights:
- Manhours: 950.000
- Manpower Peak: 330
- Key Quantities Installed
- Electrical Works
Cable Trays: 20.000 lm
Cable Conduits: 15.000 lm
Grounding System: 50.000 lm
MV/LV Cables Laying: 700.000 lm
Lighting Fixtures: 1.950 no.
Equipment: 880 no.
Cathodic Protection System: 37.000 lm - Instrumentation Works
Cable Trays: 20.000 lm
Cable Conduits: 25.000 lm
Ins Cables Laying: 320.000 lm
Junction Boxes: 650 no.
Field Instruments: 7.000 no.
Control Valves: 1.180 no.
Loop Checks: 4.500 I/O
- Electrical Works