Job Description:
Electrical & Instrumentation Works
Project Duration:
October 2009 – June 2011
Project Highlights:
- Manhours: 1.025.000
- Manpower Peak: 450
- Key Quantities Installed
- Electrical Works
Cable Trays: 75.000 lm
Cable Conduits: 90.000 lm
Grounding System: 95.000 lm
MV/LV Cables Laying: 950.000 lm
Lighting Fixtures: 2.900 no.
Equipment: 280 no.
Electrical Heat Tracing: 180.000 lm - Instrumentation Works
Cable Trays: 22.000 lm
Cable Conduits: 12.000 lm
Ins Cables Laying: 450.000 lm
Junction Boxes: 450 no.
Field Instruments: 5.000 no.
Control Valves: 900 no.
Telecommunication System: 800 no.
Loop Checks: 4.450 no.
- Electrical Works