Job Description:
Electrical & Instrumentation Works
Project Duration:
September 2019 – May 2022
Project Highlights:
- Manhours: 1.212.000
- Manpower Peak: 450
- Key Quantities Installed
- Electrical Works
Cable Trays: 250.000 lm
Cable Conduits: 150.000 lm
Grounding System: 124.000 lm
MV/LV Cables Laying: 2.026.00 lm
MV/LV Cables Connection: 23.325 no.
Lighting Fixtures: 5.033 no.
Equipment: 291 no.
Substation Container: 90 no.
Electrical Heat Tracing: 225.196 lm
Motors Test: 629 no. - Instrumentation Works
Ins Cables Laying: 540.000 lm
Ins Cables Connection: 1.506 no.
Junction Boxes: 562 no.
Field Instruments: 3.469 no.
Control Valves: 3.190 no.
Fire & Gas System: 1.060 no.
Telecommunication System: 1.060 no.
Loop Checks: 13.463 no.
- Electrical Works