Expansion of Chlorine Plant 3 (Germany)

Client:
BASF / Technip Germany

Location:
Ludwigshafen (Germany)

Job Description:
Electrical & Instrumentation Works

Project Duration:
October 2014 – December 2016

Project Highlights:

  • Manhours: 130.000
  • Manpower Peak: 85
  • Key Quantities Installed
    • Electrical Works
      Cable Conduit/Trays: 4.000 lm
      Grounding System: 5.000 lm
      MV/LV Cables Laying: 45.000 lm
      Lighting Fixtures: 1.100 no.
      MV/LV Panels: 70 no.
    • Instrumentation Works
      Ins Cables Laying: 31.500 lm
      Instrumentation Panels: 65 no.
      Field Instruments: 2.400 no.
      Telecommunication System: 50 no.
      Loop Checks: 2.200 no.
      Functional Tests: 700 no.