Job Description:
Electrical & Instrumentation Works
Project Duration:
October 2014 – December 2016
Project Highlights:
- Manhours: 130.000
- Manpower Peak: 85
- Key Quantities Installed
- Electrical Works
Cable Conduit/Trays: 4.000 lm
Grounding System: 5.000 lm
MV/LV Cables Laying: 45.000 lm
Lighting Fixtures: 1.100 no.
MV/LV Panels: 70 no. - Instrumentation Works
Ins Cables Laying: 31.500 lm
Instrumentation Panels: 65 no.
Field Instruments: 2.400 no.
Telecommunication System: 50 no.
Loop Checks: 2.200 no.
Functional Tests: 700 no.
- Electrical Works