Job Description:
Electrical & Instrumentation Works
Project Duration:
February 2010 – August 2011
Project Highlights:
- Manhours: 180.000
- Manpower Peak: 200
- Key Quantities Installed
- Electrical Works
Cable Conduits: 10.000 lm
Cable Trays: 7.500 lm
Grounding System: 15.000 lm
MV/LV Cables Laying: 300.000 lm
Lighting Fixtures: 245 no.
Equipment: 86 no. - Instrumentation Works
Cable Conduits: 2.000 lm
Cable Trays: 20.000 lm
Ins Cables Laying: 460.000 lm
Junction Boxes: 450 no.
Field Instruments: 1.500 no.
Control Valves: 200 no.
- Electrical Works